Titan-2, the main contractor in the Hanhikivi 1 project, has chosen Destia Oy to carry out earthworks for the reactor building in the nuclear power plant site.

The project, a part of preparatory work on the site, consists mainly of excavating and quarrying. The work is scheduled to start in January 2016 and to be completed by spring 2017.